Project management for incremental delivery / iterative development projects by Johanna Rothman
A rolling wave plan is a continuous detailed schedule that's only a few weeks long. As you complete one week of detailed schedule, you add another week to the end of the schedule. With a four- week rolling wave schedule, I never have less than four weeks of detailed schedule, and I never have more than four weeks of detailed schedule.